Project #756 – Brookdale Avenue & Water Street Realignment

2020-07-25T17:56:27+00:00March 1st, 2020|Earthworks & Underground|

Main work being completed (i.e. sanitary, storm and watermain install, bridge rehab or new build, specifics on the current activities, etc).

  • Sanitary sewer line starting from Tollgate Road all the way through to Cornwall Center Road. Major milestones need to be met, with trenchless boring under the CN Rail at Brookdale and the highway 401