Project #757 – Rideau Canal Bridge Rehabilitation
- Main work being completed: Girder End & Abutment Concrete Repairs
- Project location: 417 at Rideau Canal
- Project team (PM, PC/QC, Super, Foreman): Travis, Tom, Percy
- Project duration (est. start & end dates): Started May 13, 2020, Completion August 17, 2020