Project #765 – Bilberry Creek Culvert

2021-02-19T16:01:24+00:00December 17th, 2020|Structures|

  • Project Location : Orleans – Orleans Blvd. and Jeanne D’Arc Blvd.
  • Project team :
    • PM: Stephane Desjardins
    • PC: Cassidy Mercier
    • Site Superintendent: Bruno  Mongeon
  • Project duration:
    • Start: December 2020
    • Estimated Finish: May 2021
  • Brief project synopsis : Project just kicked off! Work to be done includes the replacement of a 1950mm culvert and slope

Project #763 – Rideau Canal Culvert

2020-12-14T18:46:28+00:00December 14th, 2020|Structures|

  • Project Location: Highway 15 near Joyceville
  • Project team: Mike D., Robert M., Travis S., Dominick V.
  • Project duration: Fall 2020 – November 1, 2021
  • Subcontractor is currently on site installing the stage 1 and 2 sheet pile cofferdam headwalls. Temporary bypass installation and temp asphalt were completed this fall during the pre-stage works. Structure

Project #748 – Salt Storage

2020-12-14T20:31:04+00:00July 25th, 2020|Earthworks & Underground, Structures|

Sanitary storm and watermain install, bridge rehab or new build, specifics on the current activities, etc).

Project location:

  • Cornwall Yard (1225 Ontario Street)

Project team (PM, PC/QC, Super, Foreman)

  • Sheldon Wells – Project Manager
  • Timothy MacDonald – Plante – Project Coordinator
  • Darcy Dewar – Site Supervisor
  • Andrew Wheeler – Foreman

Project duration (est. start & end dates)

  • July

Project #740 – Jones Falls Rideau Locks Stone Historical Rehab

2021-04-01T11:41:14+00:00September 25th, 2018|Structures, Water & Wastewater Treatment Facilities|

  • Project location Jones Falls Locks, Elgin, ON
  • Main work being completed: Timber bridge replacement, removal/replacement and repointing of heritage stone masonry inside of the locks, replacement of concrete lock floors, sluice tunnel repairs, sluice gate refurbishment, ladder replacement.

See also: https://www.pc.gc.ca/en/lhn-nhs/on/rideau/visit/infrastructure/rideau-lakes/masonry-maconnerie-jones-falls

Project team (PM, PC/QC, Super, Foreman)

  • PM: Mark Butzer
  • PC/QC: Ian

Project #669 – Hastings Swing Bridge

2020-09-04T14:29:14+00:00April 29th, 2016|Structures|

Client: Public Works & Government Services Canada
Location: Hastings, Ontario

Project Team:

  • Chace Albright – Project Manager
  • Mike Dillabough – Site Superintendent
  • Thomas Morency – Foreman
  • Nathan St.Louis – Forman
  • James Dineen – Estimator

The work involved concrete rehabilitation, foam injection grouting under bridge pivot pier and replacement of superstructure and systems.  This project involved winter work at