• Main work being completed: Sanitary trunk sewer over 2000m long (a lot of this work is being don on NCC property), Watermain over 450m long, modification to a pumping station, a bit of storm sewer, Herzberg road reconstruction.
  • (City: ISD12-2011, North Kanata Truck Sewer Phase 2)
  • Project location: Herzberg road Kanata. Please refer to attached site plan for full location of the project
  • Project team (PM, PC/QC, Super, Foreman): PM Nick Bray. Ass PM Stephane Desjardins, PC/QC Maxime Tremblay, Super Bruno Mongeon and Renzo Burri, Foreman past Martin Thibault future Adam Burri
  • Project duration (est. start & end dates): commence work order June 2018, contract end date November 2019, estimate actual finish December 2020 (for now)