• Main work being completed: Building foundation excavation & backfill, lot grading
  • Project location: Westboro (Ottawa)
  • Project team (PM, PC/QC, Super, Foreman): Nick, Travis, Renzo
  • Project duration (est. start & end dates): Started October 21, 2019. Completion October 6, 2020.