• Project Location: Highway 15 near Joyceville
  • Project team: Mike D., Robert M., Travis S., Dominick V.
  • Project duration: Fall 2020 – November 1, 2021
  • Subcontractor is currently on site installing the stage 1 and 2 sheet pile cofferdam headwalls. Temporary bypass installation and temp asphalt were completed this fall during the pre-stage works. Structure work will to start in Spring 2021.